The Hallmark, Manchester Build Update - Q1 2020

We are happy to bring you the latest update on how your investment is progressing at The Hallmark in Manchester. 

As you can see from the photos above, the facade and roof areas are complete and water pressure testing to external envelope is being carried out. 

Final floors are now being plastered. The apartment kitchen and bathroom fittings are progressed from the 1st to 8th floor, with floors 1-5 also painted. Please see the photos below.

3 v2
46Within the communal areas, the lifts have been installed and commissioned and the staircase walls have been plastered with handrails fitted. 

Corridor wall final mechanical and electrical systems and second boarding are being progressed. Mains services are connected to the site. 

5
7

8

Externally, the groundworks have commenced, with the car park mechanical and electrical works also progressing well. 

The contractors are still working towards handing over the building in Q2 2020, however we anticipate that this will be towards the end of Quarter 2. Completions to then take place shortly thereafter. 

In other exciting news, the show apartment on the first floor is now open and customer viewings are taking place.

We are sure you will agree how great they look below!