Park View Progress Update - December 2021

We are delighted to provide the latest update from Prosperity, detailing how the pre-construction requirements are progressing.

  • The Architect, Structural & M&E Engineers continue progressing Stage 4, pre-construction design for design freeze.
  • The Fire Consultant has been appointed to review the designs and specifications for compliance with all current and emerging building fire legislation. 
  • The piling and foundation designs are progressing in conjunction with the superstructure, and contractors are due to be instructed to carry out the works. 
  • The architect has developed the planning approved design to ensure compliance with current Building Regulations.  He has also progressed the detailed construction drawings. 
  • The design team have completed a discussion with BCC planning department to change the external fa├žade from metal cladding to brickwork, and an NMA application (non-material amendment) has been submitted for approval. 
  • Temporary supplies for electricity and water to service the site during the construction phase have been organised.
  • Mobilisation has commenced.
  • The design team continue to progress assembling fully detailed trade packages to issue to the supply chain for pricing. 
  • Electrical supply/point of connection to the site has been secured and allocated to the development site.